Data Center Workforce Camp — 32-Acre Site Civil Engineering in Childress, TX

Childress · Childress County · Texas

Industrial, Warehouse & Metal Building Development

Site plan of the 32-acre data center workforce camp in Childress, Texas, showing housing pads, internal roads and the RV park

Rapid-turnaround civil design for a 420-person camp supporting a data center build

JRH Engineering provided civil engineering design for a 32-acre workforce camp in Childress, Texas, built to house the construction workforce for a data center project — a 420-person community with a shared kitchen, recreation room and laundry facility, plus a 150-space RV park. Working directly with site contractor Diffco LLC and Energy Mechanical Services, JRH delivered the design in phases so earthwork could begin before the full civil package was complete. The whole design took 26 days.

AT A GLANCE

Project facts

  • Project type — data center workforce camp, civil engineering

  • Location — Childress, Childress County, Texas

  • Site size — 32 acres

  • Capacity — housing for 420 people, plus a 150-space RV park

  • Design timeline — 26 days, August 10 – September 4, 2026

  • Partners — Diffco LLC (site contractor), Energy Mechanical Services (mechanical and utility contractor)

  • Client — confidential

Site civil design

  • Complete site civil design for a 32-acre workforce housing community — housing pad areas, internal roadways and site grading

  • Supporting infrastructure designed for a shared kitchen, recreation room and laundry facility

  • Housing, shared facilities and RV park delivered as one coordinated site plan

Utility infrastructure

  • Utility design and coordination for a 150-space RV park

  • Utility systems designed in parallel with earthwork already underway on earlier phases

Project coordination

  • Design delivered in phases so Diffco LLC could begin earthwork while JRH continued utility design

  • One to three coordination meetings a day with Diffco LLC and Energy Mechanical Services throughout the design period

The Challenge — a full civil package in weeks, not months

The project had to move from design start to a completed civil package in a matter of weeks — a timeline with no room for the usual design-then-build sequence. Data center construction cannot start until its workforce has somewhere to live, so the camp sat on the critical path of the larger build. Housing 420 people plus a 150-space RV park on one 32-acre site also meant coordinating grading, roadways and utilities for a high-density temporary community, all under the same time pressure.

JRH’s Approach — design delivered in parts, construction started early

JRH structured the design to be delivered in parts rather than as a single finished package. Diffco LLC mobilized and began earthwork on portions of the site while JRH’s team continued designing the utility systems in parallel, instead of waiting for a complete design before construction could start. To keep both teams aligned on a schedule moving this fast, JRH held one to three coordination meetings a day with Diffco LLC and Energy Mechanical Services for the length of the design period.

The Results

01

Complete civil design delivered in 26 days for a 32-acre, 420-person data center workforce camp

02

Phased delivery let site work begin before the full design package was finished

03

Daily coordination kept design and construction moving on the same schedule

04

Housing, shared kitchen, recreation room, laundry facility and 150-space RV park delivered as one coordinated site plan

SERVICE

RELATED CASE STUDIES

Have a site like this?

Tell us the constraint. We will tell you what it takes to permit it.

FREE CONSULTATION

Let's talk about your upcoming project.

Frequently Asked Questions

​

​

​

​

​

​

bottom of page