GUIDE 08 - 2027 EDITION

Stormwater Detention Pond Quick-Reference in TX, NC, and FL

Texas, Florida & North Carolina (2027)

Rules of thumb for early planning of detention ponds by drainage area. Final sizing always requires a site- specific hydrology (H&H) analysis.

TX

4-8 ft

3:1

slopes

FL

4-8 ft

3:1

slopes

NC

3-6 ft

4:1

slopes

Typical depth and side slopes (or flatter), drainage area under 5 acres.

Important Note: The information in these guides is for general reference only. A licensed Professional Engineer should review any actual design or construction work. JRH Engineering assumes no responsibility for the application or use of these materials.

BY STATE 

Pond criteria in all three states

TX - 2027

Detention ponds in Texas

In Texas, a detention pond serving a drainage area of <5 acres typically needs 21,780–32,670 cubic feet of storage per acre, a surface area of about 1.5%–2.5% of the drainage area, depths of 4–8 ft, and side slopes of 3:1 or flatter. Larger drainage areas require a site-specific hydrology and hydraulics (H&H) study.

Drainage Area Acres
Required Volume cu ft per acre
Typical Surface Area % of drainage
Typical Length Width Ratio
Typical Depth ft
Typical Side Slopes H:V
<5
21780 - 32670
1.5 - 2.5
3:1 to 5:1
4 - 8
3:1 or flatter
5-20
32670 - 43560
2 - 3
3:1 to 5:1
5 - 10
3:1 or flatter
20-50
43560 - 54450
2.5 - 3.5
4:1 to 5:1
6 - 12
3:1 or flatter
>50
Site-specific H&H study required
2.5 - 4
4:1 minimum
6 - 15
3:1 or flatter

01

Volumes are approximate guidance. Always run site-specific hydrology per current local criteria. JRH performs full H&H studies.

Updated 2027 • Criteria based on TCEQ / iSWM / local manuals • Confirm with current county criteria

Top 5 Mistakes That Kill Approval

01

Wrong runoff coefficient → Use TCEQ / iSWM tables

02

Undersized orifice/outlet → Double-check hydraulic calculations

03

No water quality volume → Add 0.5–1.0 inch WQv

04

Poor maintenance access → Minimum 12 ft wide ramp

05

Missing emergency spillway → Required for all ponds >10 acre-ft

Notes & assumptions

FL - 2027

Detention ponds in Florida

In Florida, a detention pond serving a drainage area of <5 acres typically needs 21,780–32,670 cubic feet of storage per acre, a surface area of about 1.8%–3% of the drainage area, depths of 4–8 ft, and side slopes of 3:1 or flatter.

Drainage Area Acres
Required Volume cu ft per acre
Typical Surface Area % of drainage
Typical Length Width Ratio
Typical Depth ft
Typical Side Slopes H:V
<5
21780 - 32670
1.8 - 3
3:1 to 5:1
4 - 8
3:1 or flatter
5-20
32670 - 43560
2.2 - 3.5
3:1 to 5:1
5 - 10
3:1 or flatter
20-50
43560 - 54450
2.5 - 4
4:1 to 5:1
6 - 12
3:1 or flatter
>50
Site-specific required
3 - 4.5
4:1 minimum
6 - 15
3:1 or flatter

01

ERP process with Water Management Districts can take 90-120 days. JRH designs to current WMD criteria.

Updated 2027 • FDEP / Water Management District criteria • Confirm with SJRWMD, SFWMD, etc.

Top 5 Mistakes That Kill Approval

01

Wrong runoff coefficient → Use FDEP / WMD tables

02

Undersized orifice/outlet → Double-check hydraulic calculations

03

No water quality volume → Add required WQv

04

Poor maintenance access → Minimum 12 ft wide ramp

05

Missing emergency spillway → Required for larger ponds

Notes & assumptions

NC - 2027

Detention ponds in North Carolina

In North Carolina, a detention pond serving a drainage area of <5 acres typically needs 21,780–32,670 cubic feet of storage per acre, a surface area of about 1.5%–2.5% of the drainage area, depths of 3–6 ft, and side slopes of 4:1 or flatter.

Drainage Area Acres
Required Volume cu ft per acre
Typical Surface Area % of drainage
Typical Length Width Ratio
Typical Depth ft
Typical Side Slopes H:V
<5
21780 - 32670
1.5 - 2.5
3:1 to 5:1
3 - 6
4:1 or flatter
5-20
32670 - 43560
2 - 3
3:1 to 5:1
4 - 8
4:1 or flatter
20-50
43560 - 54450
2.5 - 3.5
4:1 to 5:1
5 - 10
4:1 or flatter
>50
Site-specific required
2.5 - 4
4:1 minimum
6 - 12
4:1 or flatter

Updated 2027 • NCDEQ criteria • Side slopes often 4:1 • Watershed nutrient rules may add requirements

Top 5 Mistakes That Kill Approval

01

Wrong runoff coefficient → Use NCDEQ tables

02

Undersized orifice/outlet → Double-check hydraulic calculations

03

No water quality volume / nutrient treatment → Address WQv and loading limits

04

Poor maintenance access → Minimum 12 ft wide ramp

05

Missing emergency spillway → Required for larger ponds

Notes & assumptions

01

Nutrient sensitive watersheds add loading limits. JRH designs full compliance packages including ESC.

Related reference guides

All 2027 reference guides

08 - Site & Civil

Subdivision Checklist & Timeline

Phase-by-phase checklist with typical durations.

04 - Permitting

Top 10 Permit Red Flags

Why permits get rejected, and the quick fix.

01 - Softs & ROI

Soft Cost Estimator

Permitting, civil, structural and stormwater soft costs.

FREE CONSULTATION

Let's talk about your upcoming project.

Frequently Asked Questions

How big does a stormwater detention pond need to be in Texas?

In Texas, a detention pond serving a drainage area of <5 acres typically needs 21,780–32,670 cubic feet of storage per acre, a surface area of about 1.5%–2.5% of the drainage area, depths of 4–8 ft, and side slopes of 3:1 or flatter. Larger drainage areas require a site-specific hydrology and hydraulics (H&H) study.

How big does a stormwater detention pond need to be in Florida?

In Florida, a detention pond serving a drainage area of <5 acres typically needs 21,780–32,670 cubic feet of storage per acre, a surface area of about 1.8%–3% of the drainage area, depths of 4–8 ft, and side slopes of 3:1 or flatter.

How big does a stormwater detention pond need to be in North Carolina?

In North Carolina, a detention pond serving a drainage area of <5 acres typically needs 21,780–32,670 cubic feet of storage per acre, a surface area of about 1.5%–2.5% of the drainage area, depths of 3–6 ft, and side slopes of 4:1 or flatter.

How current is this guide?

​This guide was updated in October 2026 for 2027. Construction costs are uplifted roughly 4% from the 2026 baseline, and references reflect ASCE 7-22 and, for Florida, the Florida Building Code 9th Edition (effective December 31, 2026).

Can I use this guide for my specific project?

No. These figures are general reference ranges, not engineering advice. Always verify current local codes, fee schedules, design criteria and site conditions with the Authority Having Jurisdiction, and contact JRH Engineering for project-specific sealed designs, estimates and permit packages.

Disclaimer: These guides are for general reference only and are not engineering advice for any specific project. Verify current local codes, fee schedules and site conditions with the Authority Having Jurisdiction.

​

Proprietary reference material of JRH Engineering. Free for personal and professional use with attribution. Commercial redistribution prohibited without written permission.

bottom of page