CASE STUDY 3 — Jordan Ranch Blvd. Office Condos 18.20-Acre Office Condo Business Park | Full Civil Engineering Design
Complete Civil Engineering Design
Office & Business Park
Brookshire · Waller County · Texas
PROJECT OVERVIEW
JRH Engineering provided complete civil engineering design for an 18.20-acre office condo business park in Brookshire, Texas, located along a TxDOT corridor requiring a new turn lane. The project demanded a drainage strategy that protected leasable square footage while satisfying MUD utility requirements and dual-agency storm sewer approval. JRH engineered a compact on-site detention system with a lift station that minimized the pond footprint and kept the most valuable land available for buildings.
AT A GLANCE
Site Civil Design
● Full site civil design including grading, paving, parking layout, and building pad configuration
● Turn lane designed to TxDOT standards on the adjacent TxDOT corridor — required for site access approval
● On-site detention system with lift station engineered to minimize pond footprint and maximize building coverage
● Compact pond placement concentrated drainage infrastructure in the least valuable portion of the site
Utility Infrastructure
● Water and sanitary sewer connections made to existing MUD district infrastructure
● MUD utility coordination run in parallel with TxDOT and drainage district permitting
● Lift station selected over gravity pond system — smaller footprint, more leasable land
Stormwater & Drainage
● On-site detention designed with lift station to reduce required pond area compared to a traditional gravity system
● Storm sewer approved concurrently through BKDD and City of Brookshire — parallel review prevented sequential delays
● Detention pond placed strategically to protect high-value building area at the front of the site
Permitting & Agency Coordination
● TxDOT turn lane permit coordinated concurrently with drainage and city approvals
● BKDD and City of Brookshire storm sewer reviews run simultaneously
● MUD utility connection coordinated in parallel with all other agency reviews
THE CHALLENGE
At 18.20 acres, Jordan Ranch Blvd. was large enough that pond placement decisions had real financial consequences — every acre of pond is an acre that cannot generate lease revenue. The TxDOT corridor also required a turn lane, adding a state agency coordination layer that runs on its own timeline regardless of how fast the local approvals move.
JRH's Approach
JRH engineered a lift station-based detention system rather than a traditional gravity pond. The lift station allowed the pond footprint to be compressed significantly — protecting the most leasable portions of the site for buildings. TxDOT, BKDD, and City of Brookshire approvals were pursued simultaneously, preventing any one agency from becoming a bottleneck.
The Result
A fully permitted, maximum-density office condo business park with protected leasable square footage and a TxDOT-compliant turn lane — delivered without sacrificing buildable land to an oversized pond.
RESULTS
● Leasable square footage protected through lift station detention system — pond footprint minimized across 18.20 acres
● TxDOT turn lane permitted concurrently with drainage district and city approvals — no sequential delays
● MUD utility connections coordinated in parallel — no utility permitting holdups