Houston Astros Diamond Club Parking Expansion — Fast-Track Civil Engineering in Houston, TX
Houston · Harris County · Texas
Institutional, Educational & Athletic Facilities

A new parking lot on a three-month deadline tied to opening day
JRH Engineering delivered complete civil engineering design for a new parking lot adjacent to Daikin Park — home of the Houston Astros — on an aggressive three-month construction deadline tied to the start of the baseball season. Construction plans were completed in under one week. The Houston Astros leveraged their relationships with the City of Houston to expedite plan review, and JRH rapid, complete submission kept that process moving without delays from the engineering side.
AT A GLANCE
Site civil design
Complete parking lot civil design including layout, grading, paving, drainage, and utility connections
Construction plans completed in under one week — a full design package produced at a pace matched to the season deadline
Complete submission package delivered to the City of Houston on first submittal — no revision cycles caused by incomplete or incorrect drawings
City of Houston expedited review leveraged by the Astros — a rapid, clean submission kept the review on track
Utility infrastructure
Water and sanitary connections made to the City of Houston system
Utility connections designed and coordinated concurrently with parking lot and drainage design
Stormwater and drainage
Drainage design integrated into the parking lot layout — stormwater managed within the site footprint
City of Houston drainage requirements met within the compressed design timeline
Permitting and agency coordination
City of Houston permit targeted to meet the construction start date required for season-opening completion
Astros city relationships used to expedite review — submission quality ensured the review process was not slowed by engineering deficiencies
Design to permitted construction-ready completed in record time
The Challenge — three months, and no time for a revision cycle
The Houston Astros had a hard deadline: the parking lot needed to be designed, permitted, and built before the season started. Three months is not a long timeline for a City of Houston permit, and the design had to be complete and correct on first submission.
JRH’s Approach — treat the one-week design target as the deliverable
Everything else followed from getting a complete, accurate construction package out the door fast. The Astros had city relationships that could accelerate review, but only if the submission gave the city nothing to push back on. JRH produced a complete package and the Astros moved it through city review on the expedited track.
The Results
01
Construction plans completed in under one week — a full civil design package delivered to meet the season deadline
02
City of Houston permit issued on time for construction completion before the season opener
03
Complete first submission — no revision cycles caused by the engineering package
04
Frequently Asked Questions
What was the main engineering challenge on the Houston Astros Diamond Club parking project?
The parking lot needed to be designed, permitted, and built before the start of the baseball season, leaving no time for revision cycles on the City of Houston permit.
How did JRH Engineering meet the season deadline for this project?
JRH completed the full construction plan set in under one week and delivered a complete submission package to the City of Houston with no engineering deficiencies, allowing the Astros' expedited review track to move without delay.
What were the results of the Houston Astros parking expansion project?
JRH completed construction plans in under one week, secured a City of Houston permit in time for construction to finish before opening day, and achieved a complete first submission with no revision cycles.