Helical Pile Foundation Design for a Custom Home in Mt. Enterprise, TX

Mt. Enterprise · Rusk County · Texas

Structural Engineering

Helical pile foundation installation for a custom home in Mt. Enterprise, Rusk County, Texas

A deep foundation system for soil that will not carry a slab

JRH Engineering provided structural foundation design for a new custom home in Mt. Enterprise, Rusk County, Texas, where soil conditions required a helical pile foundation system rather than a conventional spread-footing or slab approach. JRH scope was specifically the foundation and beam dimension design, coordinated with the project other engineering consultant on items outside JRH design scope, such as waterproofing.

AT A GLANCE

Project facts

  • Project type: custom single-family home, foundation engineering

  • Location: Mt. Enterprise, Rusk County, TX

  • Scale: single-family residence

  • Services: structural engineering, helical pile foundation design

  • Permitting agency: City of Mt. Enterprise

  • Client: confidential, private homeowner

  • Completion: Q4 2025

  • Construction value: confidential

Structural engineering

  • Helical pile foundation designed with a 25-kip design capacity per pile at a 20-foot pile length

  • Foundation plan and beam dimension plan coordinated to the architectural drawings

  • Design scope defined and coordinated alongside another engineering consultant separate scope of work on the project — waterproofing design specifically excluded from JRH scope and clearly documented as such

  • Design completed per the 2021 International Residential Code with City of Mt. Enterprise amendments

Permitting and agency coordination

  • PE-sealed foundation plans prepared for City of Mt. Enterprise building permit submission

  • Design scope boundaries clearly documented on the drawings to avoid overlap or gaps with the other consultant scope of work

The Challenge — not every lot supports a conventional footing

When soil conditions require a deep foundation system, the engineer has to size a system capable of carrying the home full load safely to depth — and, on a project with more than one engineering consultant involved, be explicit about exactly where one firm design scope ends and another begins.

JRH’s Approach — size the piles, then draw the boundary

JRH designed a helical pile foundation system sized to a 25-kip capacity per pile at 20 feet in length, verified in the field by the helical pile installer, and produced a coordinated foundation and beam dimension plan set. The drawings explicitly noted which elements — such as waterproofing — fell outside JRH scope of work, keeping responsibility boundaries clear across the project engineering team.

The Results

01

Helical pile foundation system engineered to a 25-kip capacity per pile at 20-foot length

02

Foundation and beam dimension plans coordinated with the project architectural drawings

03

Design scope explicitly documented to maintain clear responsibility boundaries with the project other engineering consultant

04

SERVICE

Have a site like this?

Tell us the constraint. We will tell you what it takes to permit it.

FREE CONSULTATION

Let's talk about your upcoming project.

Frequently Asked Questions

What was the main engineering challenge on this Mt. Enterprise, TX foundation project?

Soil conditions at the site required a helical pile foundation system rather than a conventional spread footing or slab, and the project involved a separate engineering consultant handling other scope items on the same home.

How did JRH Engineering approach the helical pile foundation design?

JRH designed a helical pile system sized to a 25-kip capacity per pile at a 20-foot pile length, and clearly documented the boundaries of JRH's design scope to avoid overlap with the project's other engineering consultant.

What were the results of this helical pile foundation project?

JRH delivered an engineered helical pile foundation system with a coordinated foundation and beam dimension plan, and PE-sealed plans prepared for City of Mt. Enterprise permit submission.